Estimating and Costing

For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_____.

  • A. 0.90 m³
  • B. 0.94 m³
  • C. 0.98 m³
  • D. 1.00 m³
Answer: Option B.
Explanation: 

No answer description available for this question.