Construction Planning and Management

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

  • A. 1
  • B. 2
  • C. 3
  • D. 4
Answer: Option A.
Explanation: 

No answer description available for this question.