Irrigation Engineering
If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be_____.
- A. 1 + (0.9)010
- B. 1 – (0.9)°l0
- C. 1/(1-0.9°10)
- D. 1/(1+ 0.9010)
No answer description available for this question.