Construction Planning and Management

In the given figure, the network of a project represents_____.

  • A. Activity of an excavation of a footing
  • B. Activity of an excavation which starts at event No. 1 and ends at even No. 2
  • C. Activity of excavation which takes 8 units of time
  • D. None of these
Answer: Option C.
Explanation:

No answer description available for this question.