Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

  • A. 20
  • B. 25
  • C. 35
  • D. 15
Answer: Option B.
Explanation: 

No answer description available for this question.