Construction Planning and Management

Pick up the incorrect statement from the following:

  • A. An activity of a project is denoted by an arrow on the net work
  • B. The tail of the arrow indicates the start of the activity
  • C. The head of the arrow indicates the end of the activity
  • D. The arrows are drawn to scale from left to right
Answer: Option D.
Explanation: 

No answer description available for this question.