Pick up the incorrect statement from the following:

  • A. The activity is the time consuming part of a project
  • B. The beginning and end of a job, are called events
  • C. The activity which consumes maximum time, is called a node
  • D. Logically and sequentially connected activities and events form a network
Answer: Option C.
Explanation: 

No answer description available for this question.