Construction Planning and Management
Pick up the incorrect statement from the following:
- A. The activity is the time consuming part of a project
- B. The beginning and end of a job, are called events
- C. The activity which consumes maximum time, is called a node
- D. Logically and sequentially connected activities and events form a network