Estimating and Costing

The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is_____.

  • A. 1.00 m³
  • B. 1.25 m³
  • C. 1.50 m³
  • D. 1.75 m³
Answer: Option B.
Explanation: 

No answer description available for this question.