The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

  • A. 1.5 m³
  • B. 2.5 m³
  • C. 3.5 m³
  • D. 5.0 m³
Answer: Option D.
Explanation: 

No answer description available for this question.