Tunnel Engineering

The following operations are generally employed for tunnelling in hard rock.
1.Removing ground water,
2.Loading holes and firing the explosive
3.Setting up and drilling
4.Grouting and lining
5.Removing muck
6.Ventilation and removing explosion dust
The correct sequence is:

  • A. 3, 2, 6, 5, 1, 4
  • B. 3, 4, 6, 1, 5, 2
  • C. 4, 1, 2, 3, 6, 5
  • D. 5, 4, 2, 1, 3, 6
Answer: Option A.
Explanation: 

IS 14665 gives details about elevators. It specifies the number, capacityof elevator and number of floors to be served.