Estimating and Costing

The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is

  • A. 3250 m³
  • B. 3225 m³
  • C. 3275 m³
  • D. 3300 m³
Answer: Option B.
Explanation: 

No answer description available for this question.