The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is
- A. (6 + 15) chains
- B. (6 + 12) chains
- C. (6 + 18) chains
- D. None of these